Getting the bridge ready for winter

By Rolland Kidder 3 min read

The snow hasn't started falling yet, but you can see that things on the Chautauqua Lake Bridge have been changing in anticipation of it.

I noticed last week that the concrete paving machines had been removed from the site indicating that the paving season was over. Concrete pouring requires temperatures above about 45 degrees, and temperatures have been hovering around the freezing point at night. The contractor was able to pour the outside railing walls out to where the new pavement ends.

The conclusion I take from all of this is that completing the paving on the south side of the bridge will be delayed until next spring.

I have also noticed that in the area where steel repairs have been going on, that additional cranes were brought in to lift the steel into place. Apparently, what happened is that the lake level dropped so low that the floating cranes could no longer operate effectively--thus requiring that others be brought in.

Perhaps the biggest news relative to the bridge is that it looks like the DOT is preparing to change the traffic pattern over the bridge in order to allow for more work to be done in preparation for reconstructing the north side of the structure.

It appears that the plan is to have the current two-lane traffic moved to the finished southeast side of the bridge as you cross it. This would enable the contractor to begin operations on the opposite northeast side, and begin steel replacement there so that things can move into high gear when the weather breaks in the spring.

What this means for local traffic is that the current westbound entrance at Bemus from Rt. 430 would be shut so that this work can commence. Traffic from Bemus wanting to get to Stow would need to go to the entrance on the Ellery Center Road in order to cross the bridge. (The old exit ramp from the bridge to Rt. 430 would then become an entrance ramp to cross to the Stow side.)

It looks like westbound traffic on I-86 may be diverted into two lanes in an area a couple of miles east of the bridge between the Bayview Rd. and Dutch Hollow Rd. bridges. A blacktop cross-over has recently been completed there.

I suppose that all of this sounds like "Greek" to many, but if you are trying to cross the lake between Bemus and Stow your routing will be affected. Traffic coming across the lake from Stow to Bemus will have to exit onto Rt. 430, as the exit toward Ellery Center and Mayville will be blocked by westbound expressway traffic.

For those who live on the Stow side of lake, nothing should change much there for now–both the entrance to the bridge and the exit from it should remain useable.

It may seem like "overkill" to subject readers who may rarely use the Chautauqua Lake bridge to all of this detail. Yet, in my own defense, I use this bridge every day, and the reconstruction of it is the largest and most expensive public works project undertaken in Chautauqua County since it was first dedicated and opened in 1982.

All of this as to possible traffic changes is, of course, subject to decisions by the DOT. But I believe that it is helpful for the public to know of changes which may be coming as the winter weather closes in on us.

Rolland Kidder is a Stow resident.