State moving forward with nuclear plans

4 min read

Gov. Kathy Hochul has announced the completion of the Master Plan for Responsible Advanced Nuclear Development in New York (Advanced Nuclear Master Plan). Demonstrating New York's leadership role in the national effort to develop new nuclear energy, the Master Plan is a comprehensive statewide roadmap to achieve the Governor's Nuclear Reliability Backbone to create five gigawatts (GW) of new nuclear power.

Co-authored by the New York State Energy Research Development Authority (NYSERDA) and the New York State Department of Public Service (DPS), and unveiled today at the State's third Nuclear Summit in Rochester, the master plan outlines coordinated state actions to support the safe and timely development and deployment of advanced nuclear power plants in upstate New York.

"Expanding emission-free, round-the-clock nuclear power is a cornerstone of my all-of-the-above approach to ensure we have enough energy to keep the lights on and costs down for New Yorkers," Hochul said. "The completed Advanced Nuclear Master Plan can serve as a national model by pairing our ambitious target of five gigawatts of new nuclear generation with a comprehensive strategy to support thoughtful development and deployment of what will be the largest buildout the country has seen in more than three decades."

Dunkirk's former NRG plant, now owned by Genover, could be a candidate for this type of power generation. It was one of eight communities to express an interest in the opportunity in 2025.

The master plan was developed in response to Hochul's 2025 directive to establish a framework supporting advanced nuclear energy development in New York. Now, the master plan will help facilitate the development of the Nuclear Reliability Backbone, which Governor Hochul directed the creation of in her 2026 State of the State, that will add 5 gigawatts of new nuclear generation to the 3.4 gigawatts already in existence.

DPS today also issued a White Paper with policy recommendations to help enable the commercial viability of advanced nuclear development, potential cost reductions and other considerations for advancing the Governor's Nuclear Reliability Backbone.

In addition, the New York Power Authority (NYPA) also continues to move forward to develop and construct at least one gigawatt of nuclear energy in Upstate New York.

Public Service Commission Chair Rory Christian said, "The Master Plan and White Paper announced today offer actionable next steps to safely and responsibly facilitate the development of 5 gigawatts of new nuclear in New York State. Thanks to the leadership of Governor Hochul, these collaborative and comprehensive interagency workstreams serve as a strong foundation to expand New York's nuclear footprint to maintain a reliable grid while centering community input and workforce opportunities."

The 30-point Advanced Nuclear Master Plan supported by 12 studies and more than 1,000 pages of research and analysis identifies New York State actions to further assist with responsible advanced nuclear development. It provides detailed findings and conclusions that address the interconnected requirements for deployment, including commercial viability, siting considerations, community partnerships, state regulatory processes, workforce readiness, and supply chain capacity. The Master Plan identifies several areas of focus to support responsible advanced nuclear development, including:

-- Advance a policy framework to support deployment: Enable State actions on cost reductions and project commercial viability.

-- Capitalize on investments: Build on federal investments and opportunities such as Project Janus at Fort Drum.

-- Maximize New York's nuclear supply chain opportunities: Establish a nuclear supplier readiness program, connect New York businesses with nuclear project opportunities, and develop a coordinated, longer-term state supply chain strategy.

-- Build the workforce for nuclear energy - starting with existing skills and resources: Leverage existing workforce funding and programs, upskill experienced workers, and support transitions from adjacent sectors while aligning specialized training investments with deployment.

-- Identify potential sites and partner with communities to prepare for development: Establish a process to identify interested host communities, evaluate suitable sites, including brownfields, and support early site characterization and evaluation.

-- Adapt state regulatory processes while maintaining uncompromising safety: Review State regulatory processes, identify opportunities to better align requirements, and equip local governments with tools to prepare for potential development.

In June 2025, Hochul called upon the New York Power Authority (NYPA) to lead the development of an advanced nuclear power project in Upstate New York capable of generating at least 1 GW of zero-emissions electricity.

Since then--in parallel with the development of this Master Plan--NYPA has advanced a focused predevelopment effort. The Power Authority has solicited information from interested host communities and potential development partners, invested in building a nuclear talent pipeline through major workforce‑development funding, expanded international partnerships to share expertise and strengthen project delivery, and grown its leadership team with seasoned nuclear experts to guide siting, licensing, financing, and deployment efforts. Eight communities expressed interest in hosting a nuclear power project, and in November, NYPA qualified ten nuclear energy developers for potential partnership.