Priority Sites: County receives $1M for culvert replacements
Trending
The town of Chautauqua will be working on replacing a pair of culverts in 2027, thanks to a pair of state WQIP grants valued at around $1 million.
Wright Road and Elmwood Road, near the Hartfield Volunteer Fire Department, were priority sites identified for construction during the planning phase of the project, which was led by the town of Chautauqua and EcoStrategies Engineering and Surveying. State grant funds were also used to identify the culverts in need of replacement and advance engineering.
Culvert work is a Priority 1 Project "necessary to manage water quality and reduce HABs in Chautauqua Lake" according to the state's Harmful Algal Bloom Action Plan. Priority 1 short-term recommendations focus on projects like sewer district extension (currently underway by the county), stream stabilization and roadside infrastructure work. In addition to maintaining basic roadway safety, culverts are crucial points in the watershed that affect erosion and nutrient runoff to local streams. Aged and undersized culverts can contribute to flooding, debris jams, and cause more dirt and "plant/algae food" to head downstream and into the lake.
The Chautauqua Highway Department is planning to perform much of the construction itself over the next several years, and work with a contractor for parts of the project that may require specialized equipment. Their work will be used as matching funds, leveraging the larger state grants necessary to complete the replacements. The town of Chautauqua and several other lakeside towns and villages have established strong track records of success with state-funded projects, leveraging smaller engineering awards into larger shovel-ready construction work. In 2026 the Town completed a construction project on over 16 miles of roadside ditches, also making use of state funds to improve water quality.
Culverts are also a high priority for the town of North Harmony right now. Greenman Pedersen Inc. is performing an engineering assessment for a site on Cedar Avenue, while a state grant has also been secured for replacement of a culvert on Carpenter Pringle Road. All of these projects will be designed and constructed to handle more frequent future storms, and pass along water quality benefits to the lake for decades.
Bringing state dollars to bear on long-term watershed improvement takes time, effort and leadership. Supervisors and mayors, village and town boards, clerks, highway departments and DPWs, and the county all have to put in hours (and often matching funds) to get this work done. Alliance members including the County's Soil and Water Conservation District and Everwild Land Trust frequently work with towns and villages on this front. While dealing with lake weeds and algae each summer can feel like a sprint, the watershed work is a marathon. Chipping away at the problem over years makes an impact, and that success becomes clearer when shovels finally go in the ground.
Thanks to all who have helped these culvert projects so far, and to all of the Alliance members who continue to bring state dollars to the aid of Chautauqua Lake. For more information visit chautauquaalliance.org/projects/.
State funding for the projects mentioned in this article was provided by the Environmental Protection Fund administered by the state DEC.