WACS gets update on project timeline
Westfield Academy and Central School Board of Education members learned about the progress and timeline for the work on the Capital Improvement Project at their meeting in June. WACS Superintendent Ryan Sikorski told board members the foundation for the new concession stand has been poured and the new scoreboard has been delivered. Also, he reported that the internal wall tiling has been laid, and is awaiting final approval before the work begins full time. Beginning this week, abatement signs were to be posted, Sikorski said. However, no work will begin until summer vacation. ...