City To Begin Streets Program This Month

Pictured is map of street work to be completed in Jamestown this summer.

The city of Jamestown will begin work on its annual streets program later in May.

Increased state aid means the city will be aggressive in implementing an expanded program. The plan focuses on the greatest areas of need for the city, and works to improve the city’s aging streets. Several projects could be added to the list as the season progresses, depending on greater funding availability, as well as weather.

“With increased funding this year we can scale up and continue to work on more CHIPS projects than in past years,” said Jeff Lehman, city public works director. “We are able to take on a large number of projects. I am proud of the work our team has done to help use this boost of funds to tackle many projects this summer.”

Projects are planned to be completed by the end of the summer/all season, depending on the weather, the flow of public funding, contractor availability and the changing price of materials. Additional summer labor positions will be added this year from the extra CHIPS funding, which will allow the city to complete more work than in years passed.

“I am encouraged by the work the DPW has done to get our streets program in a place where they can do so many projects,” said Councilman Tom Nelson, D-Ward 6 and Public Works Committee chairman. “The hard work they’ve put into a time of so much uncertainty is notable. I appreciate the chance to have input into the process and I feel as if every project that the city is going forward with is a worthy and necessary project.”

A detailed map of street projects and expected completion dates can be found on the city’s website at JamestownNY.gov/2021Streets. Every street is evaluated on the City’s Complete Streets Program to see if striped bike lanes or sharrows can be included.

MISCELLANEOUS STREETS PROJECTS – APPROXIMATE START DATE: VARIOUS

¯ Van Buren Street from Main to Prendergast: Brick and curb repair

¯ Potters Alley from 4th St. to 5th St.: New storm sewer and pavement

¯ Hughes Street at Allen Park: Repair storm sewer, new subbase and pavement

¯ Hazeltine Avenue from Sampson to Raymond: Remove brick and pave

¯ Andrews Avenue from Harding to 3rd: Curb replacement

¯ Briggs Street from Institute to Foote: Brick and curb repair

¯ Kidder Street from Prospect to Main: Total reconstruction

¯ 5th Street from Main to Pine, South Side Re-align parking spaces, new curb

¯ Jefferson Street from 8th to Isabella: Total reconstruction

¯ King Street from Allen to Ellicott: curb repair

¯ Scioto Street from Allen to Hedges: Repair storm drains and curbs

¯ Lincoln Street from 4th to 5th: Brick and curb repair

¯ Bowen Street from Bush to Falconer: Brick and curb repair

¯ Newland Avenue from Hallock to Huxley: In-place pavement recycling

¯ Roseland Park: Storm water detention work (underground detention pond)

¯ Allen Park Glen: Repairs to bridges and pools

¯ Riverwalk extension at the new Skate Park: Fairmount Ave

¯ Wildwood Avenue: Brick and curb repair

¯ Tower Street from Pullman to King: Remove brick and pave

¯ Miscellaneous pipe relining

MILL AND OVERLAY – APPROXIMATE START DATE: JUNE 1, JULY 15 & AUG 15

¯ Fairview Avenue from Harding to 100 ft North

¯ City View Avenue

¯ Prendergast Avenue from 2nd to 3rd

¯ Tiffany Avenue from 2nd to Falconer

¯ 5th Street from Main to Prendergast

¯ Ivy Street from South to Sabin

¯ Brad Street from Ivy to Foote

¯ Sabin Avenue from Main to Howard

¯ Cole Avenue from Sampson to Forest

¯ Parkview

¯ King Street from Allen to Ellicott

¯ Tower Street from Willard to English

¯ Scioto Street from Allen to Hedges

¯ Newland Avenue from Huxley to Hallock

¯ Crescent Street from Winsor to Bishop

¯ 17th Street

¯ Huxley Street from Front to Kenmore

¯ Chestnut Street from Lakeview to brick

¯ James Street from 2nd to Falconer

¯ Charlotte Street from Margaret to Falconer

NOVA CHIP – APPROXIMATE START DATE: JULY 15

¯ Parkdale Drive

¯ South Avenue from Whitehill to Main

See STREETS, Page A8

From Page A7

¯ Brad Street

¯ Maple Street from Camp to Allen

¯ Loretta Avenue

¯ Laura Street from Pardee to Swan

¯ Buffalo Street from Bowen to Main

¯ Sanford Drive

¯ Martin Road from Arterial to City line (County)

SLURRY SEAL – APPROXIMATE START DATE: JUNE 1

¯ Hillcrest Avenue

¯ Hilldale Avenue

¯ Highland Avenue from Pershing to Palmer

¯ Arden Parkway

¯ Colfax Street from Hazeltine to Wilton

¯ McKinley Street from Charles to Colfax

¯ Charles Street from McKinley to Newland

¯ Charles Street from Hazeltine to Elliot

¯ Mission Street

¯ Prather Avenue from Barret to Forest

¯ Broadhead Avenue from Prather to Kidder

¯ Broadhead Avenue from South to Smith

¯ Prospect Street from South to Smith

¯ Fairfield Avenue from Park to Myrtle

¯ Hazeltine Avenue from Park to Myrtle

¯ Smith Avenue from Myrtle to Main

¯ Evelyn Drive

¯ Jackson Avenue

¯ Fairdale Avenue

¯ Ahrens Avenue from Elm to Oak

¯ Ellicott Street from English to brick

¯ Tower Street from English to brick

¯ Pearl Avenue from Kinney to Ensign

¯ Charlotte Avenue from 2nd to Falconer

¯ James Avenue from Falconer to 1st JCC Driveway

¯ Prendergast Avenue from 3rd to 4th

¯ Buffalo Street from Bowen to Weeks

¯ Shady Lane from Everett to Elm

¯ Dearing Avenue

CHIP SEAL – APPROXIMATE START DATE: JUNE 15

¯ Lister Street from Jones and Gifford to railroad tracks

¯ Pennsylvania Avenue from Schuyler to Trenton

¯ Trenton Street Pennsylvania to Newland

¯ Maplewood Avenue (double)

¯ Pennsylvania Avenue from Baker to City View

¯ Porter Avenue

¯ Olson Avenue from State to dead-end

¯ Hazzard Street from South to Montauk

¯ Fowler Avenue from Montauk to Cole

¯ Broadhead Avenue from Newland to Cole

¯ Alfred Street

¯ Oak Street from Hunter to Shaw

¯ Auburn Avenue

¯ Pleasant Avenue

¯ Institute Street from Harrison to dead-end

¯ Benedict Avenue from Pratt to Vega

¯ Scott Street

¯ Cheney Street from Scott to Crescent

¯ Minsker Street

¯ Pratt Avenue from Allen to Buffalo

¯ Clifton Street from Fluvanna to cul-de-sac

¯ Barr Street from Gustavus to Charlotte

¯ Charlotte Street from Margaret to Barr

¯ Benedict – Dead-ends

¯ Shady Lane from Ahrens to Everett

CRACK FILL – APPROXIMATE START DATE: MAY 1

¯ Seymour Street

¯ Hallock Street from Livingston to dead-end

¯ Hallock Street from Newland to 3rd

¯ Hunt from McDaniel to City line

¯ Front Street from Mercury to McDaniel

¯ Colfax Street from Newland to Hazeltine

¯ Hazeltine Avenue from Baker to Sampson

¯ Barrett Avenue from Prather to Newland

¯ Ivy Street from Foote to Cole

¯ Prospect Street from Newland to Prather

¯ Myrtle Street from Newland to Locust

¯ Barker Street

¯ Evelyn Drive

¯ Jackson Avenue

¯ Cole Avenue from Foote to Forest

¯ Prather Avenue from Foote to Arterial

¯ Shaw Avenue from Elm to Oak

¯ Ahrens Avenue from Elm to Oak

¯ Country View Estates

¯ Prendergast Avenue from 6th to 8th

¯ Falconer Street from Niagara to Curtis

¯ Falconer Street from Stowe to Lakeview

¯ James Avenue from Falconer to 1st JCC Driveway

¯ Holman Street

¯ Kinney Street

¯ Allen Street from Institute to Foote

¯ Winsor Street from Harrison to Allen

¯ Winsor Street from 2nd to Falconer

¯ Swan Street from Crestline to Laura

¯ Anderson Street from Crestline to Laura

¯ George Avenue

¯ Willow Avenue at Willard

¯ Tiffany Avenue from Allen to Buffalo

¯ 8th Street from Fairmount to Monroe

¯ 6th Street from Bridge to Winsor

¯ 5th Street from Fairmount to Washington

¯ 4th Street from Washington to Main

¯ 4th Street from Prendergast to Spring

¯ 4th Street at Fairmount

¯ 3rd Street from Washington to Spring

¯ 2nd Street from Washington to Main

¯ Fluvanna Avenue from Washington to Main

¯ 18th Street

¯ 12th Street

¯ N. Main Street from W. Oak to Marvin

¯ N. Main Street from 15th to 17th.

“This has been an unprecedented time for our city and the budget picture has cleared to allow us to have a larger scope of projects than in years past,” said Mayor Eddie Sundquist. “I applaud all the work Jeff and his engineers did to use these extra funds to address the biggest areas of need on our city streets.”